1.Installation and commissioning

    1.1 General note

    1.2 Installation

    1) Footer installation (if required) )

    2) Correct installation is one of the conditions for good subsequent use.It must be carried out properly and meet the requirements of the technical conditions.

    Before the test run, check whether the electrical equipment is correctly connected to the design requirements,and meet the good grounding.

    Before the test run, it must be ensured that each reducer and bearing have enough lubricant.

    No-load test run continuous operation for more than 2 hours ,then check the correctness of the equipment assembly, found to be not in line with the following conditions should be immediately stop, treat and run again until it is in good operating condition.

    2. Operation

    2.1 Commissioning and operation

    Before the first test run of the equipment, it must be checked strictly according to the following points:

    Do not operate the machine without training or authorization!

    Do not operate the machine without authorization.If there is any safety hazard, stop using it.Make sure it is safe to use.

    2.2 Debugging

    The hand auto button  is turned to the manual position, the feed motor runs, the knife clicks run, the shaftless screw motor runs, the dust collection motor runs, and the inclined screw motor runs ,then the green run start button light is on, press red button to stop.

    Hand automatic button is turned to the automatic position, press the alarm reset & initialization, the equipment will be initialized, initialization is completed pause indicator light flashes, press the green run button, the run indicator light is always on, you can manually carry the bag of materials to the belt machine (if changed to robotic handling need to rectify the system). Press the yellow pause button, pause indicator light is always on. If it runs again, press the green run button. Every time the machine is switched on or after a malfunction is lifted, the alarm must be reset & initialized.

    Left main power :main switch. three-phase power: feed power, cutter motor,screw motors,Dust collection motor and inclined screw motor.

    If the cylinder magnetic switch is not in place for 10s or the thermal relay protection action fault indicator flashes, press the emergency stop button and enter the equipment to deal with why the cylinder magnetic switch is not in place, or open the distribution cabinet to reset the thermal relay.

    Tap the hydraulic lifting mechanism, need to ensure that lifting in place and return to the low position accurately, the low position has a buffer pad, need to be installed reliably. Need to check the oil circuit, pipeline, pump station without oil leakage.

    Equipment servicing:The cutter belt is checked weekly and cleaned up , the motor is checked monthly if  overload and lack or oil light and cleaned up , the cylinder is checked and cleaned up once in two weeks, the bearing seat grease injection port grease injection and the hydraulic pump station is overhauled once a month, and all of them are overhauled and cleaned up every half a year, and the dust filter cartridges are checked whether they are broken or not once every two months.

    Note: The electric hoist must not be tilted for lifting

    Make sure that the power supply is disconnected before starting to operate the equipment.

    The motor current should always be kept within the rated current,and if it is frequently overloaded, the feeding quantity should be reduced. The operator of the control system should be able to visualize the current change of the main motor in order to adjust the feeding volume of the feeder in time to avoid any unexpected accidents!

    2.3 Stop running

    Turn off the plate feeders feeding the unit in sequence from a distance, and then turn off the unit after the plate feeders have come to a standstill. Security measure is ready , then can use .